Ceilings, floors and pipe wrap removed from a 1930s duplex before it comes down
Example project
- Home
- 1930s duplex in Santa Monica, two units of about 650 sq ft each, with textured ceilings, kitchen linoleum and a crawl space
- Original request
- Take the duplex down and build a new two-unit building on the lot
- Testing
- A whole-building survey by a Cal/OSHA-certified asbestos consultant, about 30 samples from both units and the crawl space
- Found
- Asbestos in the ceiling texture, the kitchen linoleum with its glue and the wrap on the water pipes under the floor
- Clear
- The wall plaster and the window putty
- Area
- About 900 sq ft of ceiling, 400 sq ft of floor and 90 ft of pipe wrap
- Timeline
- Notice no later than 10 working days ahead, then five working days before the wrecking crew
- Cost
- $24,500
In this example, an owner is replacing a 1930s duplex with a new building. Santa Monica collects the Rule 1403 notification form and an asbestos report when it issues the demolition permit, so the survey and the district notice are finished before the permit comes through.